Home MenuBeechnut Park Improvement Project
Project No.
63063
Location
Beechnut Park
About the Project
This project will replace the existing playground surface and equipment and upgrade picnic facilities. Aging trees surrounding the playground will be replaced with lower height trees to accommodate the PG&E power line easement.
Public Works Contact
Jose Pacheco
Associate Engineer
jpacheco@herculesca.gov
(510) 799-8247
Contractor
TBD
Project Updates
February 2026 - Final design was awarded at the February 24, 2026 City Council meeting. Construction anticipated late summer/fall 2026.
November 2025 - Encroachment permit approved. 100% Design pending.
August 2025 - Encroachment permit submitted to PG&E for CPUC approval.
June 2025 - Third party request to use PG&E overhead power easement submitted. Currently in design. Construction anticipated to occur in 2026.