The work consists of CCTV inspection of the following:
| item |
quantity |
location on as-builts |
| 30-inch HDPE pipe |
4,124 LF |
C01 to C09 and C11 to C12 |
| 12-inch HDPE pipe |
469 LF |
C09 to C11 |
| 24-inch pipe cured-in-place pipe lining |
991 LF |
C09 to C11 |
| 18-inch storm drain |
~200 LF |
C06 and C07 |
| 8-inch HDPE sliplined pipe |
~110 LF |
C05 |
| 8-inch PVC sewer main |
350 LF |
C07 |
| 23 manholes |
|
C01 to C12 |
| 3 vaults |
|
C02 and C07 |
The locations of the segments are shown on the as-built construction plans provided in Attachment 1 of the RFP.
Warranty CCTV Inspection of Lower Sycamore Avenue Trunk Sewer Request for Proposal